The Cau Nuoc Xanh Industrial Park was granted Investment Certificate No. 35 121 000221 on June 20, 2011, and amended for the first time on November 4, 2014. The project was officially established according to Decision No. 3314/QD-UBND dated September 20, 2016, issued by the People’s Committee of Binh Dinh Province.

With a total investment of approximately 80 billion VND, the industrial cluster covers an area of ​​378,277 m² (equivalent to 38.78 hectares). Construction began in the first quarter of 2013 and the project commenced operations in the fourth quarter of 2015.

Details

Industrial park name

Cau Nuoc Xanh Industrial Park 

Location

Binh Nghi Commune, Tay Son District, Binh Dinh Province

Total area

38,78 hectares

Occupancy rate

38%

Infrastructure information

Electrical system

1600KVA transformer substation

Water system

 

Sewage system

500 cubic meters of water per day/night

Transportation system

 

1. Project overview and legal information

AVA Consulting proudly presents an overview of the Cau Nuoc Xanh Industrial Park:

  • Project Name: Cau Nuoc Xanh Industrial Park
  • Location: Binh Nghi Commune, Tay Son District, Binh Dinh Province
  • Area: 38.78 hectares
  • Operating Period: 50 years (2011 – 2061)
  • Occupancy Rate: Approximately 38%

Investment Sectors:
The industrial cluster focuses on developing agricultural and forestry processing industries, aligning with the region’s strengths.

Currently, the Cau Nuoc Xanh Industrial Cluster has achieved an occupancy rate of approximately 37.6%, with about 18 hectares of land remaining available for interested investors.

2. Investment costs and incentives

The following fees apply within the industrial park:

  • Infrastructure management and maintenance fee: 0.5 USD/m²/year
  • Raw land lease fee (annual): Based on the price set by the People’s Committee of Thua Thien Hue province
  • Electricity price: Ranging from 0.03 – 0.1 USD/kWh, depending on the usage timeframe
  • Water price: 0.4 USD/m³
  • Wastewater treatment fee: 0.28 USD/m³, where the wastewater volume is calculated as 80% of the total water consumption

Investment incentives at Cau Nuoc Xanh Industrial Park:

  • Land lease fee:
    Investors are exempt from land lease fees for 15 years.
  • Corporate income tax (CIT):
    A preferential tax rate of 10% is applied for 15 years; tax is exempted for the first 4 years and reduced by 50% for the following 9 years.
  • Import tax:
    Exemption from import tax for goods imported to be used in the formation of fixed assets for the project.

Lucky Star Company is investing in the construction of a modified cassava starch production plant in the Cau Nuoc Xanh Industrial Park.

  • Infrastructure maintenance fee: 0.2 USD/m²
  • Other service costs: Including electricity, water, wastewater treatment, telecommunications (telephone, internet, etc.) are applied according to current State regulations and will be specifically stipulated in the contract between the investor and the relevant service providers.

3. Geographical location of Cau Nuoc Xanh Industrial Park

The Cau Nuoc Xanh Industrial Park boasts a prime location right on National Highway 19B, a route connecting to Gia Lai province, and is only about 2 km from Phu Phong town. This allows businesses easy access to transportation, circulation, and import/export of goods.

Regional Links:

  • East: Borders Nuoc Xanh stream
  • West: Borders Phu An cemetery (Tay Xuan commune) and rice paddies
  • South: Borders Chop Vang mountain
  • North: Borders the National Highway 19 corridor

Distance:

  • Distance to Quy Nhon City: approximately 40 km
  • Distance to Quy Nhon Port: approximately 40 km
  • Distance to Dieu Tri train station: approximately 30 km

4. Infrastructure System

The Cau Nuoc Xanh Industrial Park has been invested with a basic technical infrastructure system to meet the operational needs of businesses, including:

  • Electricity supply system:
    Equipped with a 1,600 KVA transformer station, which is currently being upgraded to better meet the electricity needs of investors.
  • Clean water supply system:
    Clean water is supplied from the district’s water supply system, with a connection point already arranged to the industrial cluster gate and expected to be ready for connection and supply from June 2024.
  • Wastewater treatment system:
    A wastewater treatment plant with a capacity of 500 m³/day has been completed and connected to the receiving source, ensuring it meets the wastewater treatment needs of the area.